Baldy 19 is the CSE Software Engineering Instructional Lab. It hosts CSE programming and software engineering course recitations.
Baldy 19 Calendar
May 14, 2019. Baldy 19 in its 'before' state (west-facing view).
May 14, 2019. Baldy 19 in its 'before' state (east-facing view).
June 5, 2019 (and many years before). An existing Axis 2100 security camera. Foolproof security unless a criminal mastermind is clever enough to unplug its unsecured Ethernet cable.
June 5, 2019. Corrigan Moving has moved all of Baldy 19's contents to temporary storage (east-facing view).
June 5, 2019. Corrigan Moving has moved all of Baldy 19's contents to temporary storage (west-facing view).
July 19, 2019. Dave, Carl, and Artie from the Paint Shop have begun patching the walls and have painted the wire mold raceways and power poles.
July 24, 2019. Painting's done! Dave, Carl, and Artie applied Sherwin-Williams 'Silver Quill' paint color on the long (north and south) walls and Sherwin-Williams 'Software' paint color on the short (east and west) walls, the power poles, and the door trim.
Auguest 14, 2019. Justin McConchie and the Electrical Shop have installed the circuits for the perimeter monitors and the circuits for the laptop charging cart (in the southeast corner).
August 22, 2019. Tim and Sujata make final carpet layout decisions.
August 22, 2019. GP Flooring begins to remove the existing carpet.
August 22, 2019. GP Flooring has the carpeting mostly installed. They just need to cut in a few color pops and install the vinyl cove along the wall base.
August 26, 2019. GP Flooring has finished installing the carpet.
August 26, 2019. Tim specified the carpet to extend through the threshold, giving the entrances an integrated look that they've never had before.
August 28, 2019. Prentice has begun delivering and installing the furniture.
August 29, 2019. Furniture installation continues.
August 29, 2019. Furniture installation begins.
August 30, 2019. Furniture installed!
September 9, 2019. Justin has installed the user-accessible electrical and USB outlets above each perimeter table. He also relocated four monitor outlets that wouldn't have been concealed behind the monitors.
September, 20, 2019. Prentice is replacing the perimeter table rail mounts with less obtrusive-looking black brackets. This picture shows a table mounted with a rail.
September 23, 2019. The table remounted with unobtrusive brackets.
October 17, 2019. The UB Paint Shop (Dave, Greg, and Karl) have repaired the damage on the walls introduced by subsequent contractors following the original paint job in July.
October 30, 2019. Southtowns AV has begun running cable and installing the monitors.
October 30, 2019. Southtowns AV has mounted the first monitor.
November 6, 2019. Southtowns AV has mounted, cabled, and installed all the north wall monitors.
November 13, 2019. Southtowns AV has installed the south wall monitors.
December 20, 2019. Audio-Video Corporation delivers our Miller Presentation Systems podium.
December 23, 2019. Alan Hunt donated an Echo Dot to the lab, for entertainment or to be cannibalized for research.
December 23, 2019. Southtowns Audio-Video installs the podium and its internal media system (front).
December 23, 2019. Southtowns Audio-Video installs the podium and its internal media system (back).
Over the last five years, Baldy 19 has hosted class labs/course recitations for these courses:
For personal assistance, email the appropriate support team below.
CSE Departmental Inquiries: cse-dept@buffalo.edu
CSE Graduate Program (Prospective Students): gradeng@buffalo.edu
CSE Graduate Program (Current Students): csegradcoord@buffalo.edu
CSE Undergraduate Program: cse-uginfo@buffalo.edu
CSE Information Technology Services: cse-consult@buffalo.edu
MyUB is the online portal that connects you to tons of important information you can use every day. At MyUB, you can:
MyUB also gives you access to the HUB Student Center.